|

1
The History of Steam 2 English 3
Physics 4 Maths 5
Economics 6 Boilogy 7
Geography of a process plant 8
Chemistry
9
Civics
-
IBR Rules - Standards and agencies
10
Quick Reference 11
Steam Table
|
IBR
Rules.
What
is IBR? IBR
stands for The Indian Boiler Regulations Act 1920 (with subsequent
amendments). It is an Act of Law, and is therefore actual law in
the country. It governs the manufacture, installation, operation
and maintenance of Steam Boilers.
In the early 1900's when
steam boilers first became widely used for industrial purposes,
the simple control systems and high steam pressures caused a
number of accidents. To prevent this, the British Government set
up a British Boiler Regulation which specified that a Government
Inspector would be responsible and would have to certify all steam
boiler as suitable from a safety and engineering point of view.
This was copied as the IBR in 1920. Thus, the IBR is not a “type”
approval, in which once a certain type of design is approved, each
unit does not need approval. Instead, it is a specific approval
for each and every unit – every boiler, every valve, every
trap, every pipe and so on.
With the development of better
materials, safer control systems, advanced manufacturing
techniques etc., it became pointless to have a government
inspection for each and every unit, and every other country in the
world has moved on to either self compliance to specified
standards, or at most a type approval system. However, the IBR
still specifies a unit approval, and every item used in an IBR
steam system has to be manufactured, installed, tested, operated
and maintained under the watchful eye of our dear local
inspector.
How
does it apply to our customers? Every
customer who runs an IBR boiler has to have an annual IBR
inpsection by an IBR inspector. The local IBR office is a state
government department, and maintains satellite offices close to
each industrial zone, and they have to be invited to inspect the
boiler and system.
What
is an IBR boiler? A
steam boiler is defined in the IBR act as a vessel containing
greater than 22.5 litres of water which is used to generate steam.
Generally, any boiler above 1000 Kg/hr capacity is an IBR boiler.
Non IBR boilers are coil type water tube boilers, available in a
capacity of 200 – 850 Kg/hr. Note that no pressure is
specified in this regulation. What this means is that it is
possible to have a small coil type boiler generating steam at 100
bar, and it is classified as a Non IBR boiler, as long as coil
volume is below 22.5 litres.
What
is an IBR system? The
Act defines anything connected to an IBR Boiler as an IBR system
i.e. All boiler mountings, steam distribution pipes, valves,
traps, strainers etc. are all under IBR. The only concession
provided here is that once the pressure of steam is dropped below
3.5 Kg/cm2g (50 psig), the system becomes Non IBR. This is why
most process plants use 3.5 Kg/cm2g as process steam.
Note
that a steam pipe connected to a single (or bank of multiple) Non
IBR boilers is not an IBR line, as it is not connected to an IBR
boiler, no matter what pressure it is operating at.
Where
does IBR scope end? As
stated earlier, a system is non IBR if one of the following is
true: The boiler or boilers are Non IBR coil type boilers The
steam pressure is dropped below 3.5 Kg/cm2g At the last valve
before the process equipment (the process equipment is again Non
IBR, no matter what pressure it operates at) Condensate is not
steam – it is water – and is therefore exempt from
IBR Thats why steam traps on the main lines have to be IBR, but
traps installed on the process equipment are Non IBR.
What
does IBR mean for a manufacturer of steam equipment? An
IBR licence is required to manufacture steam equipment –
this is a factory approval, even before the unit can make and
valve or pipe etc., and is given to those shops where adequate
infrastructure exists for pressurised joint welding, testing
etc.
A drawing of the product (with the client's name) has
to be made and submitted for provisional IBR approval, and the
corresponding fees paid
Once the approval is received, raw
materials have to be purchased from IBR approved vendors, and each
and every part has to have an IBR approval certificate
The
inspector has to be called to inspect and approve the material
before proceeding
The manufacturing can now be started,
but must use welding methods and fabrication procedures as
specified by IBR
The inspector has to be called back for
inspection and approval of Tack welding
The manufacturing
is now completed, full welding etc. dome
The inspector has
to be called back to inspect and approve hydrostatic and other
testing
Once approved, the as-built drawing along with all
inspection reports and drawings has to be submitted back to the
IBR office for final approval.
Note that all this has to be
done whether you are making a boiler, or simply attaching a one
foot piece of pipe to a flange.
All this means a lot of
extra cost, a lot of extra time, and basically a custom built
product for each and every application. It also involves planning,
adequate delivery period, liaison with inspectors etc.
What
does IBR mean for a manufacturer of steam equipment? An IBR
license is required to manufacture steam equipment – this is
a factory approval, even before the unit can make and valve or
pipe etc., and is given to those shops where adequate
infrastructure exists for pressurised joint welding, testing
etc.
A drawing of the product (with the client's name) has
to be made and submitted for provisional IBR approval, and the
corresponding fees paid
Once the approval is received, raw
materials have to be purchased from IBR approved vendors, and each
and every part has to have an IBR approval certificate
The
inspector has to be called to inspect and approve the material
before proceeding
The manufacturing can now be started,
but must use welding methods and fabrication procedures as
specified by IBR
The inspector has to be called back for
inspection and approval of Tack welding
The manufacturing
is now completed, full welding etc. dome
The inspector has
to be called back to inspect and approve hydrostatic and other
testing
Once approved, the as-built drawing along with all
inspection reports and drawings has to be submitted back to the
IBR office for final approval.
Note that all this has to be
done whether you are making a boiler, or simply attaching a one
foot piece of pipe to a flange.
All this means a lot of
extra cost, a lot of extra time, and basically a custom built
product for each and every application. It also involves planning,
adequate delivery period, liasion with inspectors etc.
Standards
and agencies.
ANSI
B31.1&3 Piping Standards (American) ASTM A 106
Specifications for Carbon Steel Pipes IS 1239
Specifications for ERW Pipes ANSI B 16.5 Steel Pipe
Flanges & Flanged Fittings ANSI B 16.10 Face to face
dimensions of ferrous valves ANSI B16.11 Threaded Pipe
Fittings ASTM A 105 Specifications for Forged
Valves ASTM A 216 Specifications for casting for Carbon
Steel Valves ASTM A234 Forged Carbon Steel Pipe
Fittings
Pic. The standards library
IS 2712 Gaskets for Fluid Flow Piping ASTM
A193/4 HT Fasteners IS 1367 Fasteners for industrial
service

Copyright
© Steamline 2010
|